Report underlines importance of Longannet for future of energy security.

The National Grid’s Winter Review and Consultation report found that the margin of spare generating capacity could be as low as 1.2% for this coming winter, compared to a margin of 4.1% last winter.

The report presents a review of the security of supply in gas and electricity for the last winter (2014/15) and launches an industry consultation on National Grid’s forecasts for the coming winter (2015/16), which will conclude in August.

Energy Minister Fergus Ewing says the situation shows complacency by the UK Government and added that next year the margins could be under even greater pressure if Longannet is forced to close prematurely.

The current transmission charging regime for Great Britain was introduced by the UK Government in 2005. Since then, successive UK Governments have failed to address the significant disincentive to any new thermal generation in Scotland which these charges present.

The UK Government’s policy continues to impact negatively on the existing thermal generating capability in Scotland, and in particular on the potential for new power stations to be built.

Mr Ewing said:

“These figures show that the national grid is becoming even harder pressed to keep the lights on this winter.

“Thermal energy is a source of generation which has a significant impact on grid capacity margins and can enhance energy security.

“At a time when the UK Government is presiding over a period of extremely narrow generation capacity margins, it has chosen not to intervene regarding the unfair transmission charges which are threatening the future of thermal generation in Scotland.

“Given the need to address shrinking capacity margins it makes no sense to cancel planned onshore wind developments, as the UK government is doing through the removal of financial support. The situation of narrowing capacity margins will only be exacerbated if Longannet closes prematurely.

“It is vital, therefore, that all possible options for averting the premature closure of the Longannet site are explored, such as action to address discriminatory transmission charges. The Scottish Government has raised these concerns at the highest level in the UK Government and is engaging all relevant authorities and agencies alongside Scottish Power to secure the best possible outcomes for those affected throughout the local economy and further afield by the uncertainty of the site.”

Contact Information

SG Communications

SGCommunications@scot.gov.uk

Chris Nabney

chris.nabney@scot.gov.uk

Channel website: http://www.gov.scot/

Share this article

Latest News from
Scottish Government