Transport for London
Printable version

TfL’s construction projects to commence phased restart

Work has resumed on the Bank Station Capacity Upgrade, the Northern Line Extension and the transformation of Old Street Roundabout, with shifts staggered.

Work on a number of TfL construction projects has resumed with more restarting in the coming weeks, in line with the Government's announcement in early May easing lockdown measures for those who could not work from home.

Construction at around 300 TfL sites was brought to a Safe Stop in late March to help prevent the spread of coronavirus.

Since then design and other preparatory work on many of these projects has continued, with staff and many of TfL's contractors working from home.

During the next few weeks, site preparation to accommodate social distancing and construction work will safely begin in a phased way on a number of projects vital to supporting jobs and homes, or providing essential transport infrastructure, across the capital.

These include major capacity improvements and extensions for Tube and rail, such as the Northern Line Extension to Battersea, the Bank Station Capacity Upgrade and the extension of London Overground to the new housing development at Barking Riverside.

They also include the transformation of Old Street Roundabout, Cycleways, safety improvements to some key road junctions and new walking and cycling infrastructure to support social distancing by encouraging active travel.

Safely and quickly

TfL has worked closely with its contractors and supply chain to introduce changes to ensure all sites operate safely and fully comply with the latest guidance from the Government and Public Health England.

Extensive physical changes to worksites and ways of working are being introduced by TfL and its contractors to ensure sites can reopen as safely and quickly as possible and help all workers stay safe and maintain social distancing. These include:

  • staggered shifts and breaks to spread journeys outside peak periods and prevent large groups
  • clear signage for social distancing and one-way walking routes
  • additional staff welfare areas
  • additional hand-washing facilities and sanitising stations
  • reconfigured canteens and access to personal hand sanitisers

All sites will have a reduced number of people working at any one time, with some sites having an additional Site Supervisor to ensure social distancing is maintained.

Workers will be further supported at some sites by Welfare Wardens who will control access to common areas and changing facilities, so they do not become crowded.

Deliveries to sites are also being adapted. Every effort is being made to keep deliveries to a minimum and any delivery drivers must now enter sites with windows wound up. Instead of signing for goods being delivered, photographs are being taken.

Heidi Alexander, Deputy Mayor for Transport, said: 

“It's really positive that work can now safely resume on key transport infrastructure projects, which will help to kickstart London's economic recovery.

“It's vital that construction workers make journeys to sites on foot or by bike if at all possible in order to keep services safe for those who really need it. If workers have to travel on public transport, I'm pleased that our plans for staggered shifts will help them avoid the busiest times.”

Stuart Harvey, Director of Major Projects, said: 

“Our number one priority is always the safety of staff on our sites as well as the surrounding communities. We have carefully developed our plans and adapted our worksites by working closely with our supply chain.

“It is a positive step that work can safely recommence on upgrades and key transport infrastructure projects that are so vital for the capital.

“We will continue to keep activity at all sites under review and ensure we continuously evaluate and improve our approach with safety at the forefront of all that we do.”

New ways of working

All staff are being actively encouraged to walk or cycle to work if they can and avoid public transport where possible.

TfL is investigating options to allow the construction sector to privately hire river boats and provide transport for workers at construction sites accessible from the river.

As work resumes, TfL will assess what effect the new ways of working will have on delivery schedules for the individual projects, subject to longer-term funding being received.

Opportunities to restart work on other projects continue to be reviewed across TfL's capital delivery programme and further updates will follow as soon as they are available.

Notes to Editors

  • Over the coming weeks a phased restart will continue on Bank Station Capacity Upgrade, the Northern Line Extension, Four Lines Modernisation, Barking Riverside Extension, the renovation of the Central line fleet and safety improvements at Old Street roundabout. Work will shortly resume on Cycleway 4 (Tower Bridge to Rotherhithe Roundabout) and Cycleway 9 (Brentford to Olympia)
  • Work will also restart on some step-free access improvements at stations including Cockfosters, Harrow on the Hill, Mill Hill East and Wimbledon Park, as well as station enhancements at Bromley by Bow, Finsbury Park, Knightsbridge and Tottenham Hale. Asset renewal works on DLR, Trams and London Overground are also due to resume
  • Main construction works on the Silvertown Tunnel are not planned until later in the year, however, work on on-site surveys and other activities to support the ongoing design and construction planning will now restart
  • In line with the latest government guidance, physical work at Crossrail sites has now resumed. All Crossrail sites continue to observe strict social distancing protocols with the numbers of people at each location strictly limited at all times

TfL travel advice for those working in the construction sector is as follows:

  • Please continue to work from home if you can. If you have to travel for work, please allow plenty of time, plan ahead by identifying alternative routes and options such as cycling or walking
  • To help make space for those who must travel on public transport you should walk or cycle unless unable to do so
  • If you have to use public transport, please avoid peak times (05:45-08:15 and 16:00-17:30), and busy interchanges wherever possible. Consider whether you could start or end your journey using quieter stations. (For instance, by walking the first or last part of journeys). To help plan journeys TfL has published details of the busiest stations and lines. You can find the list here and our walking tube map here
  • If using public transport, or taxi and private hire services, please use a facial covering, carry a hand sanitiser and wash your hands before and after you travel
  • Advice on maintaining social distancing will be given across the transport network and further measures to prevent crowding through new queuing systems will be in operation. Please respect each other's space and try to maintain social distancing wherever possible
  • Hardworking staff are there to help - please act on their instructions and respect them at all times
  • If you have to drive, please plan ahead and obey speed limits and traffic laws at all times

 

Channel website: https://tfl.gov.uk/