National Audit Office Press Releases
Printable version

The Transpennine Route Upgrade Programme

Government has put the Transpennine Route rail upgrade on a firmer footing, but there remains a risk of delays and cost increases, and it is not yet clear how the upgrade’s intended benefits will be achieved, according to the National Audit Office (NAO).

The Transpennine rail route provides the most direct rail link between Manchester and Leeds, as well as connecting smaller towns and commuter areas in the north of England. In 2011, the Department for Transport (the Department) first announced its intention to improve the route through the Transpennine Route Upgrade Programme (the Programme). In its Integrated Rail Plan in November 2021, the Department announced that the Programme would be delivered as Phase One of Northern Powerhouse Rail.1

The Department has developed a clear case for investment in the Transpennine route, but it has taken too long to decide how to upgrade it. In the decade prior to the COVID-19 pandemic, passenger journeys provided by the two main train operators of the route increased from 106 million to 137 million, resulting in overcrowding. Work on the Programme first started in 2015 but was paused. Since 2017, the Department has repeatedly altered the scope of the Programme to meet differing ministerial priorities and budget constraints. As a result, £190 million of the £1 billion Network Rail has spent on the Programme has been on work no longer needed.

The Department has committed to the Programme as a core element of its plan for rail in the north of England and the Midlands. The scope includes additional track to increase capacity for passenger and freight services and to improve journey reliability. As at May 2021, the Department forecast that the Programme will cost between £9 billion and £11.5 billion in cash terms and that it will be completed between 2036 and 2041.

Negotiations between Network Rail and train operators to agree track access for construction work on the route will be difficult, which creates a risk of delays. Network Rail must gain repeated access to the track for construction, disrupting train and freight operators, and therefore passengers and businesses. The Programme will also need buy-in from local leaders, businesses and landowners for timely access to land and to agree development.

The Department has not yet committed to funding the rolling stock needed to achieve the Programme’s full benefits. The upgraded route will require electric trains that are compatible with new signalling systems. Until funding is confirmed there is no certainty that rolling stock will be at the required level.

It is not yet clear how the Department and Network Rail will manage the cost of inflation. The Department and Network Rail have not yet agreed how sharp rises in the cost of energy and materials will be funded. It is also not clear if Network Rail and supply chain contractors will be able to fully address labour shortages, which may also increase costs.

Passengers’ awareness of the planned upgrades to the Transpennine route is low, which is a concern because of the disruption it may cause to their journeys.2This creates a risk that passengers will switch to other forms of transport to avoid disruption during upgrade works and will not return in the long-term. Network Rail is developing its communications approach with train operators and plans a large marketing campaign for autumn 2022. It is also minimising the use of rail replacement bus services throughout the Programme as they are unpopular with passengers.

The Department and Network Rail are taking reasonable steps to set up the Programme for success, including applying lessons from other major infrastructure projects. It is still at an early stage, and the real test will come as construction work begins in earnest. However, by now the NAO would expect Network Rail and the Department to know how success will be measured. The NAO also finds that:

  • It is not yet clear how other government departments and local government will help deliver the Programme’s benefits;
  • It has not been determined how the Programme will be managed as part of Northern Powerhouse Rail to ensure the benefits and connections between the two projects are fully aligned; and
  • It is not yet clear if the Programme’s design will provide long-term resilience to climate change.

The NAO recommends that the Department and Network Rail set out how they will measure the benefits of the Programme, such as reduced carbon emissions, and that they should also monitor the impact of disruption on passengers.

Gareth Davies, the head of the NAO said:  “Rail passengers in the north have contended with increasing over-crowding and delays for too long. It is good that plans for the Transpennine Route upgrade are now agreed, but there are still significant risks to the programme’s progress that could cause further disruption. The Department for Transport, Network Rail and government must work together to manage these challenges and deliver the expected benefits for rail users.”

Full report:  The Transpennine Route Upgrade Programme

Notes for Editors

  1. In November 2021, the Department for Transport published its Integrated Rail Plan for the North and Midlands. One element of this plan is Northern Powerhouse Rail, through which government intends to significantly improve connectivity between the north of England’s major economic centres. The Transpennine Route Upgrade Programme will now be delivered as Phase One of Northern Powerhouse Rail.
  2. Research by Transport Focus in summer 2019 and Network Rail in spring 2022 found low passenger awareness of the Programme and concerns about the disruption it could cause.
  3. Press notices and reports are available from the date of publication on the NAO website. Hard copies can be obtained by using the relevant links on our website.

About the NAO

The National Audit Office (NAO) scrutinises public spending for Parliament and is independent of government and the civil service. It helps Parliament hold government to account and it uses its insights to help people who manage and govern public bodies improve public services.

The Comptroller and Auditor General (C&AG), Gareth Davies, is an Officer of the House of Commons and leads the NAO. The NAO audits the financial accounts of departments and other public bodies. It also examines and reports on the value for money of how public money has been spent.

In 2021, the NAO's work led to a positive financial impact through reduced costs, improved service delivery, or other benefits to citizens, of £874 million.

Channel website: https://www.nao.org.uk/

Original article link: https://www.nao.org.uk/press-release/the-transpennine-route-upgrade-programme/

Share this article

Latest News from
National Audit Office Press Releases

Exclusive offers, deals and discounts available to public sector staff, past and present!