How shared vision led to the ‘timely’ and ‘on budget’ delivery of Thames Tideway Tunnel project

21 Nov 2025 11:51 AM

At the end of October, a new ‘micro park’ opened in London which was built out into the River Thames to house part of the super sewer infrastructure below ground. This new public space is just one example of the benefits being realised by the Thames Tideway Tunnel project. APM spoke to Tideway, the company delivering the project, to find out how a clear sense of purpose helped its successful delivery.

The delivery of the Thames Tideway Tunnel project has been cited by the British press as “a masterclass in bringing a major infrastructure project in on time and within budget.” While there’s nothing new about the media focusing on ‘iron triangle’ metrics, what really makes the project stand out are the benefits it’s delivering and the way in which these have been delivered as part of a wider, shared vision.

Work on the Thames Tideway Tunnel began in 2016. The project’s aim is to transform the health of the River Thames by eliminating the harmful effects of sewage pollution. By February 2025, the tunnel was connected and protecting the River Thames. The project is due to be fully up and running (with testing complete) by the end of 2025. Once finished, Tideway anticipates that the super sewer will virtually eliminate the harmful effects of sewage pollution on the River Thames through central London. Thames Water will then operate the system, as part of its London wastewater network.

Working as One

The Tideway Tunnel project’s delivery success lies in its alliance of contractors. The west region is being delivered by a joint venture of BAM Nuttall, Morgan Sindall Infrastructure and Balfour Beatty. The central region is being delivered by a joint venture of Ferrovial Agroman UK and Laing O'Rourke. The east region is being delivered by a joint venture of Costain, Vinci Construction Grands Projets and Bachy Soletanche. 

Although Tideway was presented as a unified project, its delivery relied on the programme team to manage the controls, logistics and stakeholder engagement across all these groups to ensuring smooth integration. The success of this collaboration was driven by the shared vision and clarity of purpose the project had.

“The CEO, Andy Mitchell, and the board were very clear about the aspirations for the project from the outset,” Andy Alder, Thames Tideway’s Programme Director until summer 2023, said. “Tideway has a critical environmental purpose that included creating new public places on the river and reconnecting people with the Thames. It was viewed as a once in a lifetime project to create new land in London.”

For the Thames Tunnel project, the shared vision was achieved through:

A shared vision helps project delivery in several ways:

In addition to its core purpose of creating a cleaner, healthier River Thames, other benefits delivered by the project include: 

If you’re interested in learning more about Tideway, the upcoming winter issue of Project features an in-depth commentary from Tideway’s Chief Executive, Andy Mitchell CBE. Project is the official quarterly journal of Association for Project Management (APM). APM members receive Project free as part of their member benefits package. If you’re already not a member, you can join here.