Planning application decision times published

29 Jan 2019 01:38 PM

An Official Statistics Publication for Scotland

Statistics on quarterly planning performance in Scotland have been released today by Scotland’s Chief Statistician. These detail the number of planning applications decided across Scotland and average decision times for most types of application including housing.

The overall average decision time for all local applications concluded in the first six months of 2018/19 (8.9 weeks for 13,391 applications) was the same as for the equivalent period in the previous year. In addition, there were 1,051 local developments decided that had processing agreements in place, with 786 (75%) of these meeting agreed timescales.

The overall average decision time for all major developments concluded in the first six months of 2018/19 (34.6 weeks for 112 applications) was 1.6 weeks quicker than for the same period in the previous year (36.2 weeks). In addition, there were 61 major applications decided that were subject to processing agreements with 43 (70%) of these meeting agreed timescales.

Key Findings for Quarters 1 and 2 (April to September) of 2018/19:

The overall average decision time for all local applications decided in the first six months of 2018/19 matched the decision time for the equivalent period in 2017/18.

The average decision time for local housing developments decided in the first six months of 2018/19 was quicker by almost three days than the equivalent period in 2017/18.

The overall average decision time for all major developments decided in the first six months of 2018/19 was over a week and a half quicker compared to the equivalent period in 2017/18.

The average decision time for major housing developments decided in the first six months of 2018/19 was quicker by almost four weeks compared to the same period in 2017/18.

The overall rate of approvals for all types of application[1] (including legacy applications) was 93.7% in the first quarter of 2018/19 and 93.5% in quarter two. These were both slightly lower than the corresponding rates of 94.1% and 93.9% for the respective quarters in the previous year.

The figures released today were produced in accordance with professional standards set out in the Code of Practice for Official Statistics.

Notes to Editors

The average decision time figures presented in this Statistical News Release exclude applications validated prior to 3rd August 2009 which are considered legacy cases, and applications concluded through the use of a processing agreement between the developer and the local authority, where an agreement on timescales for decisions can be made either at the beginning of the application process or at a later stage. Also, some applications exclude time periods in which particular delays have been outwith the control of planning authorities. Further information on these types of application is available in the full statistical publication.

Local developments include applications for changes to individual houses and smaller developments for new housing as well as applications covering areas of development such as minerals, business & industry, waste management, electricity generation, freshwater fish farming, marine finfish farming, marine shellfish farming, telecommunications, Approval of Matters Specified in Conditions (AMSCs[2]) and other developments.

Major developments include applications for 50 or more homes, as well as certain waste, water, transport and energy-related developments, larger retail developments, and other developments.

Classification between local and major developments depends on the particular development type. For example, housing developments are classed as major when the application is for 50 or more dwellings or for a site that exceeds two hectares, whereas electricity generation is classed as major when the capacity of the generating station is or exceeds 20 megawatts.

An explanatory document providing background information on the Planning Performance Framework is also available.

Official statistics are produced in accordance with professional standards – more information on the standards of official statistics in Scotland can be accessed at: http://www.scotland.gov.uk/Topics/Statistics/About

[1] Decisions on applications classified as N17 Other consents and certificates are not included in the calculation of approval rates.

[2] Applications for Approval of Matters Specified in Conditions (AMSCs) relate to conditions attached to planning permission in principle requiring the further approval, consent or agreement of the planning authority for any detailed aspect of the development.