HSE PUBLISHES SELLAFIELD 'ONE YEAR ON' REPORT
22 Feb 2001 12:00 AM
The Health & Safety Executive (HSE) today published a report on
progress by British Nuclear Fuels plc (BNFL) in responding to three
HSE reports on Sellafield, published in February 2000.
Today''s report, by HSE''s Nuclear Installations Inspectorate (NII),
describes how inspectors have tested BNFL''s responses and measures
for improvement at Sellafield. It also gives an update on clearance
of the 65 recommendations contained in the reports, which covered MOX
fuel data falsification; control and supervision of operations; and
liquid waste storage.
Laurence Williams, HM Chief Inspector of Nuclear Installations, said
today: ''Overall, we are encouraged by the vigour and commitment that
BNFL has given to addressing the issues raised by all three reports.
This has been a highly challenging year for BNFL and our inspectors.
A considerable amount of work has been undertaken but more remains to
be done.''
All 15 recommendations in the MOX data falsification report have been
satisfactorily addressed and NII inspectors have ''closed out'' all of
them. NII will regulate restart of the MOX Demonstration Facility in
the same way as other Sellafield plants and BNFL has been required to
submit a re-commissioning safety report.
''BNFL has also taken significant action in response to the report on
HSE''s inspection of control and supervision.'' The BNFL Board has been
restructured and the Sellafield management reorganised to provide a
single individual who is responsible for operations and safety at the
site. Greater clarity of roles and responsibilities have been
identified and staffing at Sellafield has increased.
There has been good progress against most of the 28 team inspection
report recommendations, three having been formally ''closed out.''
Experience has shown formal closeout will take longer than previously
envisaged, due to the time required for changes to be implemented and
for evidence of this to be provided. This will affect the timescale
for final ''closeout.'' Hence, NII has asked BNFL to review its plans
for all of the outstanding recommendations.
''The High Level Waste report recommendations required BNFL to develop
a strategy for reducing stocks of ''high active liquid waste stored at
Sellafield and improvements to the safety case for the plants holding
this waste.'' All 22 recommendations have now been cleared following
extensive discussions on BNFL''s submissions. BNFL has also provided
an updated safety case, supported by a programme of operational and
engineering improvements.''
NII has issued a Specification to enforce an agreed stock reduction
strategy and NII will carry out a critical review of BNFL''s strategy
every two years to look for further reductions. NII''s views will be
reported, as part of normal regulatory activity, via the Sellafield
Local Liaison Committee (LLC). Reports to LLCs are placed on HSE''s
website.
Copies of the report, ''Progress on BNFL''s response to three reports
issued by HSE on 18 February 2000'', are available free from
Information Centre, Nuclear Safety Directorate, HSE, Room 004, St.
Peter''s House, Balliol Road, Bootle, Merseyside L20 3LZ (Tel: 0151
951 4103/Fax: 0151 951 4004). The report is also available on HSE''s
website at www.hse.gov.uk/nsd/bnflprog01.pdf
Notes to Editors
1. NII is the part of HSE responsible for regulating safety at
Sellafield and all other nuclear licensed sites in the UK. BNFL holds
a licence from HSE, granted under the Nuclear Installations Act 1965
(as amended), to operate Sellafield, and is subject to site licence
conditions. The Sellafield site contains two types of nuclear
installations. Four Magnox reactors provide steam and electricity for
the site and supply electricity to the national grid. The rest of the
site, comprising several hundred buildings, is associated with the
reprocessing of spent nuclear fuel and treatment and storage of
radioactive wastes.
2. NII investigated and analysed in detail the issues surrounding
falsification of MOX fuel quality assurance (QA) data, first reported
by BNFL in September 1999. NII''s report concluded that: a systematic
management failure allowed various individuals to falsify QA records
for fuel pellet diameter measurements; it was not possible to
establish a motive, but poor ergonomic design of the plant, tedium of
the job and the ease with which the data logging system could be
manipulated were seen to be contributory factors; and that, although
data was falsified, this would have no effect on the safety of the
fuel in a nuclear reactor. In December 2000, NII announced it had
accepted BNFL''s responses to all 15 recommendations (see press notice
E247:00 of 19 December 2000).
3. During the first half of 1999, NII detected an apparent increase
in the number of incidents occurring at Sellafield. Investigation of
some of these events showed that inadequacies in BNFL''s arrangements
for the control and supervision of operations appeared to be a
significant contributor to the poor safety performance. HM Chief
Inspector of Nuclear Installations ordered that a team inspection be
carried out on the theme of control and supervision. The inspection
was carried out in September 1999 at the facilities associated with
reprocessing and waste treatment/storage. HSE required BNFL to
produce a programme for responding to the report''s 28 recommendations
within two months.
4. On 31 January 2001, NII issued BNFL with a Specification (a legal
requirement to take action) to formalise BNFL''s programme for
reducing liquid high level radioactive waste stocks at Sellafield to
a buffer level of 200 cubic metres by 2015 (see press notice E015:01
of 31 January 2001).
5. In last February''s report on liquid high level waste storage, NII
undertook to issue reports on progress with stock reduction options
and safety case improvements. This will be done through an addendum
to last year''s report, due to be published in Spring 2001, which will
describe in more detail NII''s view of BNFL''s responses to the 22
recommendations in last year''s report.
6. The three reports referred to above are:-
''An investigation into the falsification of pellet diameter data in
the MOX Demonstration Facility at the BNFL Sellafield site and the
effect of this on the safety of MOX fuel in use'';
''HSE team inspection of the control and supervision of operations at
BNFL''s Sellafield site'';
''The storage of liquid high level waste at BNFL Sellafield - an
updated review of safety''.
Copies are available free from Nuclear Safety Directorate Information
Centre, HSE, Room 004, St Peter''s House, Balliol Road, Bootle,
Merseyside L20 3LZ (Tel: 0151 951 4103/Fax: 0151 951 4004/e-mail:
nsd.infocentre@hse.gov.uk).
PUBLIC ENQUIRIES: Nuclear Safety Directorate Information Centre, HSE,
St. Peter''s House, Balliol Road, Bootle L20 3LZ (Tel: 0151-951
4103/Fax: 0151-951 4004/e-mail: nsd.infocentre@hse.gsi.gov.uk).
PRESS ENQUIRIES: Journalists only: Mark Wheeler 020 7717 6915. Out
of hours enquiries: 020 7928 8382.
HSE information and press releases can be accessed on the
Internet at www.hse.gov.uk
Ends