HEALTH AND SAFETY
EXECUTIVE News Release (E013:07) issued by The Government News
Network on 2 April 2007
Following
extensive consultation with the construction industry, the new
Construction (Design and Management) Regulations 2007 (CDM 2007)
come in to force on Friday 6 April 2007. Making it easier for duty
holders to comply with the requirements, they simplify and clarify
existing Regulations.
Through a focus on managing risks on site, reducing paper work,
encouraging team work and getting the right people for the right
job at the right time, the implementation of these Regulations are
expected to see a step change improvement in health and safety
performance within the industry.
Construction remains one of the highest risk sectors, with over
one fatality occurring each week despite the improvements made in
recent years. The revised CDM Regulations aim to improve the level
of health and safety performance in the construction industry by
clarifying the responsibilities of each duty holder and focusing
on effective planning and risk management.
Commenting on what is a landmark for the construction industry
this year, Stephen Williams, Chief Inspector of Construction, HSE
said: "The industry has worked very closely with HSE to
revise the CDM Regulations and ensure that there are clear
benefits for all competent dutyholders. The Regulations clarify
responsibilities of each duty holder and require greater focus on
the risks to be managed by all involved in the construction
process. Underlying all the changes is one simple aim - to reduce
the unacceptable number of fatalities and injuries in the
construction industry."
The revised CDM Regulations will introduce the following
changes:
* Clarify construction client responsibilities when
they are exercising their influence over the health and safety
standards on their projects.
* Replace the role of Planning Supervisor with a new role of CDM
co-ordinator. The co-ordinator will act as the client's key
advisor on health and safety issues, particularly effective
communication and co-ordination of health and safety information.
* Emphasise the importance of competence at all levels in
securing health and safety benefits, whilst simplifying the
assessment of competence.
* Drive out needless health and safety paperwork and bureaucracy.
Paperwork should be project-specific, relevant, proportionate to
the risk, and of real use in helping to manage the risk.
* Simplify when a project is notifiable, and formal plans and
appointments are required. Projects will be notifiable if they
will involve more than 30 days or 500 person days of construction
work. No projects for a domestic client will be notifiable. Formal
plans and appointments are only required for notifiable
projects.
The CDM 2007 Regulations have been developed in line
with the Government's Better Regulation principles and will
consolidate and revise the main pieces of existing construction
health and safety at work legislation, namely: the Construction
(Design and Management) Regulations 1994 and the Construction
(Health, Safety and Welfare) Regulations 1996- resulting in a
single, simplified set of regulations.
Notes to Editors:
1. The CDM Regulations have been developed
with the support of industry stakeholders and the Health and
Safety Commission's Construction Industry Advisory Committee
(CONIAC) and its CDM working group. More information for
dutyholders will be available in the ACoP 'Managing health
and safety in construction'.
2. Copies of "Managing health and safety in
construction", ISBN 9780717662234, price £15.00, will be
available from HSE Books by the end of February 2007, PO Box 1999,
Sudbury, Suffolk CO10 2WA, tel: 01787-881165 or fax: 01787-313995.
Priced publications are also available from good
booksellers.
More information on HSE's Construction
Division can be found at http://www.hse.gov.uk/construction/index.htm
Public enquiries
HSE's InfoLine 0845
3450055
Caerphilly Business Park, Caerphilly CF83 3GG
HSE information and news releases can be accessed on the Internet
http://www.hse.gov.uk/